敏捷与混合实践 中等 Process 过程域 题号 PMP202611-297

题目

某项目采用混合方式:监管文档阶段为预测型且有固定截止日期,软件功能则以敏捷冲刺交付。软件团队速率低于预期。项目经理应如何应对?
A project is using a hybrid approach. The regulatory documentation phase is predictive with a fixed deadline, while the software features are delivered in agile sprints. The software team's velocity is lower than expected. How should the project manager respond?

选项

  1. A.Extend the regulatory deadline to accommodate the agile team's actual velocity.
  2. B.Add more developers to the agile team to immediately improve velocity.
  3. C.Force the agile team to adopt predictive planning to bring velocity under control.
  4. D.Work with the agile team to identify velocity impediments, adjust the scope of features to be delivered, and assess whether the reduced velocity impacts the fixed regulatory deadline.
正确答案:D

解析

解析:D 正确。混合项目中两条流水线必须协调管理。识别障碍能触及速率低的根因;调整功能范围是敏捷的正当手段;评估对固定监管期限的影响则维持了混合项目的整体衔接。强制改预测型(C)会毁掉敏捷的收益;加人(B)按布鲁克斯定律往往短期反而降速;延长监管期限(A)通常不可行。 Rationale:D is correct. In a hybrid project, both streams must be managed coherently. Identifying impediments addresses the root cause of low velocity. Adjusting feature scope is a legitimate agile response. Assessing the impact on the fixed regulatory deadline ensures the hybrid integration is maintained. Forcing predictive planning (C) destroys agile's benefits. Adding developers (B), Brooks' Law, often reduces velocity initially. Extending a regulatory deadline (A) may not be possible.