看板与流动管理 · PMP 练习题解析

敏捷与混合实践 困难 Process 过程域 题号 PMP202611-292

题目

某使用看板的团队有大量工作项长时间卡在“进行中”列。最有效的干预是什么?
A team using Kanban is experiencing a high number of work items stuck in the "In Progress" column for extended periods. What is the most effective intervention?

选项

  1. A.Move stuck items back to the backlog and replace them with easier items.
  2. B.Extend sprint duration to give more time to complete stuck items.
  3. C.Introduce or lower Work In Progress (WIP) limits to force the team to complete items before starting new ones, and identify systemic blockers.
  4. D.Add more team members to work on the stuck items simultaneously.
正确答案:C

解析

解析:C 正确。事项卡在“进行中”说明要么在制品上限过高(同时开工太多),要么存在系统性阻碍。看板的核心机制就是在制品上限:限制并行数量能暴露瓶颈、迫使专注,从而改善流动。加人(D)可能缓解个别阻碍但改不了系统;退回事项(A)是回避问题;看板本就不使用冲刺周期(B)。 Rationale:C is correct. Items stuck in "In Progress" indicate either WIP limits are too high (allowing too many concurrent items) or there are systemic blockers. Kanban's core mechanic is WIP limits: constraining work in progress improves flow by surfacing bottlenecks and forcing focus. Adding people (D) may help with specific blockers but doesn't fix the system. Moving items back (A) avoids the problem. Kanban doesn't use sprint duration (B).