资源规划与获取 · PMP 练习题解析

资源管理 中等 People 人域 题号 PMP202611-289

题目

项目进入收尾阶段。一名老成员申请提前释放,去参加下周启动的另一个项目,而其剩余工作至关重要。项目经理应该怎么做?
A project is in its final phase. A long-standing team member requests to be released early to join another project that starts next week. Their remaining work is critical. What should the project manager do?

选项

  1. A.Refuse the request, the team member must complete their commitments before releasing.
  2. B.Have an honest conversation about the impact of early release, explore options (knowledge transfer, partial overlap, phased release) and work with both the team member and functional manager to find the best outcome for both projects.
  3. C.Ask the sponsor to intervene and prevent the release.
  4. D.Immediately approve the release to maintain a positive relationship with the team member.
正确答案:B

解析

解析:B 正确。人员流动需要协商与创造性方案,而不是简单的批准/拒绝。分阶段释放、离开前完成知识转移、短期重叠等安排,可能同时满足两边需要。一概拒绝(A)无视成员职业发展,伤士气;立即批准(D)无视项目风险;请发起人介入(C)完全跳过了协商。 Rationale:B is correct. Resource transitions require negotiation and creative solutions rather than binary approve/deny decisions. Options like a phased release, knowledge transfer before departure, or a brief overlap may satisfy both needs. An outright refusal (A) ignores the team member's career needs and may damage morale. Immediate approval (D) ignores project risk. Sponsor intervention (C) skips the negotiation step entirely.