题目
冲刺评审时,一位关键相关方说:“我没想到这个功能是这样运行的,这不是我要的。”而团队完全按验收标准实现了功能。问题出在哪,接下来该怎么办?
At sprint review, a key stakeholder says "I didn't realise the feature would work this way: this isn't what I wanted." The team built exactly what the acceptance criteria specified. What went wrong and what should happen next?
选项
- A.The acceptance criteria did not capture the stakeholder's true intent. Add a new story to the backlog reflecting the actual requirement and prioritise it with the PO.
- B.The team failed to meet the requirement: rebuild the feature at no schedule cost.
- C.Escalate to the sponsor to adjudicate between the team and the stakeholder.
- D.The stakeholder is being unreasonable, the team delivered what was agreed.
解析
解析:A 正确。这是典型的“技术上符合规格、但没抓住真实需要”的情况。冲刺评审的存在正是为了暴露这类反馈。敏捷的做法是把差距当作新认知,新增待办故事并重排优先级,而不是争论谁对。责怪团队(B)不成立,因为规格已满足;否定相关方(D)会破坏信任;这种事走升级(C)没有必要。
Rationale:A is correct. This is a classic case of requirements that were technically correct but didn't capture the real need. Sprint review exists precisely to surface this kind of feedback. The agile response is to treat the gap as new learning, create a backlog story, and reprioritise, not to debate who was right. Blaming the team (B) is incorrect since they met the specification. Dismissing the stakeholder (D) destroys trust. Escalation (C) is unnecessary for a normal product feedback conversation.
同考点练习题
-
PMP202611-106 · 答案 D
-
PMP202611-263 · 答案 B
-
PMP202611-348 · 答案 B
-
PMP202611-604 · 答案 B