题目
两位职能经理都声称项目上的一名共享资源归自己管辖。该资源对优先事项感到困惑,生产力受到影响。项目经理应该怎么做?
Two functional managers are both claiming that a shared resource on the project reports to them. The resource is confused about priorities and productivity is suffering. What should the project manager do?
选项
- A.Release the resource back to the functional managers and find a dedicated replacement.
- B.Meet with both functional managers together to clarify the resource's project role, time allocation and decision authority, and document the agreement.
- C.Tell the resource to follow only the project manager's instructions and ignore the functional managers.
- D.Ask the resource to manage their own priorities between the competing demands.
解析
解析:B 正确。矩阵型组织中的冲突需要各方共同直接解决。三方会议明确角色、投入时间与汇报线,才能一致消除歧义。让资源无视职能经理(C)只会加剧冲突;退回资源(A)未必可行,也未触及系统性问题;让资源自行权衡(D)是把压力不当转嫁给他。
Rationale:B is correct. Matrix organisation conflicts require direct resolution between all parties. A joint meeting that defines the resource's role, allocated time and reporting lines removes ambiguity for everyone. Telling the resource to ignore functional managers (C) creates further conflict. Releasing the resource (A) may not be possible and doesn't address the systemic issue. Asking the resource to self-manage competing demands (D) puts inappropriate pressure on them.