题目
某项目立项是为支持开拓新市场的战略目标。执行到一半时,公司战略调整,目标市场被降级。项目经理应该怎么做?
A project was initiated to support a strategic objective of expanding into a new market. Halfway through execution, the company's strategy changes and the target market is deprioritised. What should the project manager do?
选项
- A.Raise the strategic misalignment with the sponsor and governance body, provide an updated business case assessment, and allow them to decide whether to continue, modify or terminate the project.
- B.Rewrite the project charter to align with the new strategic direction without consulting stakeholders.
- C.Immediately stop the project and reallocate resources to other initiatives.
- D.Continue the project as planned since the original business case has already been approved.
解析
解析:A 正确。项目必须持续证明其与组织战略的一致性。一旦一致性丧失,项目经理的责任是向恰当的决策者揭示问题,而不是单方面继续或叫停。是否仍有足够价值,由发起人与治理机构决定。照旧推进(D)无视战略错配;立即叫停(C)超越项目经理权限;单方面重写章程(B)绕过正当治理。
Rationale:A is correct. Projects must continuously justify their alignment to organisational strategy. When alignment is lost, the project manager's responsibility is to surface this to the appropriate decision-makers, not to unilaterally continue or stop. The sponsor and governance body decide whether the project still delivers sufficient value. Continuing unchanged (D) ignores the strategic misalignment. Stopping immediately (C) exceeds the PM's authority. Rewriting the charter unilaterally (B) bypasses proper governance.