整体变更控制 · PMP 练习题解析

整合管理 困难 Process 过程域 题号 PMP202611-260

题目

一位相关方提出范围变更请求,将为项目增加重要功能。项目经理认为该变更很有价值。项目经理首先应该怎么做?
A stakeholder requests a scope change that would add significant functionality to the project. The project manager believes the change is valuable. What should the project manager do first?

选项

  1. A.Submit a formal change request and assess the impact on scope, schedule, cost and risk before seeking approval.
  2. B.Implement the change since it adds value to the project.
  3. C.Reject the change to protect the current project baseline.
  4. D.Ask the team to evaluate the change and implement it if they agree it is beneficial.
正确答案:A

解析

解析:A 正确。无论价值如何,所有变更都必须走整体变更控制。项目经理的职责是推动流程,而不是凭个人判断批准或拒绝。正式变更请求加影响评估,才能为决策者提供所需信息。无流程直接实施(B)造成范围蔓延;一概拒绝(C)并非项目经理可做的决定;由团队评估后直接实施(D)绕过变更治理。 Rationale:A is correct. All changes, regardless of perceived value, must go through integrated change control. The project manager's role is to facilitate the process, not to approve or reject based on personal judgment. A formal change request with impact assessment gives decision-makers the information they need. Implementing without process (B) creates scope creep. Blanket rejection (C) is not the PM's decision to make. Team evaluation without formal process (D) bypasses change control governance.

同考点练习题