整体变更控制 · PMP 练习题解析

整合管理 中等 Process 过程域 题号 PMP202611-262

题目

某项目 CPI 为 0.85,SPI 为 0.92,已完成计划工作的 40%。项目经理最恰当的做法是什么?
A project's CPI is 0.85 and SPI is 0.92. The project has completed 40% of its planned work. What is the most appropriate action for the project manager?

选项

  1. A.Identify the root cause of the cost and schedule variance, implement corrective actions, and update the project management plan.
  2. B.Immediately request additional budget from the sponsor to address the cost overrun.
  3. C.Continue monitoring: both metrics are close enough to 1.0 to be acceptable.
  4. D.Reduce scope to bring the project back within budget and schedule.
正确答案:A

解析

解析:A 正确。CPI 0.85 意味着每花 1 美元只产出 0.85 美元价值,成本超支 15%;SPI 0.92 说明进度也落后。两者都需要调查与纠正。先做根因分析,再实施纠正措施并更新计划,这正是监控过程循环。只监控(C)无视明确警示;申请预算(B)不解决底层低效;削减范围(D)是需相关方批准的重大决定。 Rationale:A is correct. CPI of 0.85 means for every $1 spent, only $0.85 of value is being delivered, a 15% cost overrun. SPI of 0.92 means the project is also behind schedule. Both require investigation and corrective action. Root cause analysis first, then corrective action and plan update. This is the Monitor & Control cycle. Simply monitoring (C) ignores a clear warning. Requesting budget (B) doesn't solve the underlying inefficiency. Reducing scope (D) is a major decision requiring stakeholder approval.