题目
某 Scrum 团队的速率稳定为每个冲刺 40 个故事点,产品待办中共有 320 个故事点。完成该待办需要多少个冲刺?
A Scrum team's velocity has been consistently 40 story points per sprint. The product backlog contains 320 story points. How many sprints are needed to complete the backlog?
选项
- A.It cannot be determined from velocity alone.
- B.6 sprints
- C.10 sprints
- D.8 sprints
解析
解析:D 正确。所需冲刺数 = 待办总量 ÷ 速率 = 320 ÷ 40 = 8 个冲刺。这是基于速率的直接预测。实际中待办会随新事项增加,因此这是最乐观估计,但就题给信息而言 8 个正确。选项 A 在真实复杂情境下成立,但考试要求给出计算结果。
Rationale:D is correct. Sprints needed = Backlog ÷ Velocity = 320 ÷ 40 = 8 sprints. This is a straightforward velocity-based forecast. In practice, backlogs grow as new items are discovered, so this is a best-case estimate, but based on the information given, 8 is correct. A would be correct in a real-world nuanced context but the exam expects the calculation answer.