敏捷度量:速率与燃尽 · PMP 练习题解析

敏捷与混合实践 困难 Process 过程域 题号 PMP202611-259

题目

某 Scrum 团队的速率稳定为每个冲刺 40 个故事点,产品待办中共有 320 个故事点。完成该待办需要多少个冲刺?
A Scrum team's velocity has been consistently 40 story points per sprint. The product backlog contains 320 story points. How many sprints are needed to complete the backlog?

选项

  1. A.It cannot be determined from velocity alone.
  2. B.6 sprints
  3. C.10 sprints
  4. D.8 sprints
正确答案:D

解析

解析:D 正确。所需冲刺数 = 待办总量 ÷ 速率 = 320 ÷ 40 = 8 个冲刺。这是基于速率的直接预测。实际中待办会随新事项增加,因此这是最乐观估计,但就题给信息而言 8 个正确。选项 A 在真实复杂情境下成立,但考试要求给出计算结果。 Rationale:D is correct. Sprints needed = Backlog ÷ Velocity = 320 ÷ 40 = 8 sprints. This is a straightforward velocity-based forecast. In practice, backlogs grow as new items are discovered, so this is a best-case estimate, but based on the information given, 8 is correct. A would be correct in a real-world nuanced context but the exam expects the calculation answer.