矩阵型组织与资源协商 · PMP 练习题解析

资源管理 困难 People 人域 题号 PMP202611-254

题目

项目经理正在组建跨部门团队。两位部门负责人为争夺一名共享成员的影响力而相互竞争,造成紧张局面。项目经理应该怎么做?
A project manager is building a cross-functional team from different departments. Two department heads are competing for influence over a shared team member, creating tension. What should the project manager do?

选项

  1. A.Remove the shared team member and hire a dedicated resource to eliminate the conflict.
  2. B.Escalate to senior management to resolve the territorial dispute between department heads.
  3. C.Clarify the team member's project role, reporting lines and time allocation in the project charter and ensure all parties agree.
  4. D.Ask the team member to decide whose guidance they prefer to follow.
正确答案:C

解析

解析:C 正确。在矩阵型组织中,角色清晰是最有效的预防手段。在项目章程中写明该成员的项目角色、汇报关系与投入时间,为各方提供正式依据,消除歧义。上报高层(B)跳过了项目经理自身的解决工具;让成员自己选边(D)把压力不当转嫁;更换资源(A)成本高且未解决根因。 Rationale:C is correct. Role clarity is the most effective preventive measure in matrix organisations. Documenting the team member's project role, reporting relationship and time commitment in the project charter gives all parties a formal reference and removes ambiguity. Escalating to senior management (B) skips the PM's own resolution tools. Asking the team member to choose (D) puts inappropriate pressure on them. Replacing the resource (A) is expensive and doesn't address the root cause.