三重约束与知情决策 · PMP 练习题解析

整合管理 中等 Process 过程域 题号 PMP202611-244

题目

项目有硬性截止日期和固定范围,但你怀疑预算偏低。根据三重约束,你应如何沟通?
A project has a hard deadline and fixed scope, but you suspect the budget is too low. According to the triple constraint, what should you communicate?

选项

  1. A.That you can deliver fixed scope, time and cost regardless.
  2. B.That fixing scope and time may require flexibility on cost, and trade-offs must be discussed.
  3. C.That cost is the only constraint that ever matters.
  4. D.That the team will simply work harder to absorb the gap.
正确答案:B

解析

解析:约束相互制约,固定范围与时间就可能需要成本弹性,必须如实摆出权衡。明知预算不足还承诺三者全固定,等于预定失败;靠“更努力”不是计划,还会带来倦怠。 Rationale:Constraints are interdependent, so fixing scope and time may require flexibility on cost; the trade-offs must be surfaced honestly. Promising all three fixed despite a budget gap sets up failure; relying on harder work is not a plan and risks burnout.