资源管理 困难 People 人域 题号 PMP202611-246

题目

一个 Scrum 团队中两位资深开发人员因关键功能的技术方案产生冲突。Scrum Master 已主持两次回顾会议仍未解决,冲刺速率下降 30%。Scrum Master 接下来应该怎么做?
A Scrum team is experiencing conflict between two senior developers over the technical approach for a critical feature. The Scrum Master has facilitated two retrospectives without resolution. Sprint velocity has dropped 30%. What should the Scrum Master do next?

选项

  1. A.Facilitate a structured one-on-one conversation between the two developers to understand each perspective, then bring them together to reach a team decision.
  2. B.Tell the team to vote on the technical approach and accept the majority decision.
  3. C.Escalate the conflict to the Product Owner and ask them to make the final technical decision.
  4. D.Remove one of the developers from the sprint to eliminate the source of conflict.
正确答案:A

解析

解析:A 正确。Scrum Master 的职责是促进解决,而不是上报或强加决定。先一对一、再共同对话,能让双方都被听到,并由团队自己拥有解决方案,符合仆人式领导。上报产品负责人(C)绕过了团队自主权;移除成员(D)处理过重;简单投票(B)没有触及冲突根源,还可能埋下怨气。 Rationale:A is correct. The Scrum Master's role is to facilitate resolution, not escalate or impose decisions. A structured one-on-one followed by a joint conversation allows both parties to be heard and empowers the team to own the solution: consistent with servant leadership. Escalating to the PO (C) bypasses team autonomy. Removing a developer (D) is disproportionate. A simple vote (B) doesn't address the underlying conflict and may create resentment.