题目
一个 Scrum 团队中两位资深开发人员因关键功能的技术方案产生冲突。Scrum Master 已主持两次回顾会议仍未解决,冲刺速率下降 30%。Scrum Master 接下来应该怎么做?
A Scrum team is experiencing conflict between two senior developers over the technical approach for a critical feature. The Scrum Master has facilitated two retrospectives without resolution. Sprint velocity has dropped 30%. What should the Scrum Master do next?
选项
- A.Facilitate a structured one-on-one conversation between the two developers to understand each perspective, then bring them together to reach a team decision.
- B.Tell the team to vote on the technical approach and accept the majority decision.
- C.Escalate the conflict to the Product Owner and ask them to make the final technical decision.
- D.Remove one of the developers from the sprint to eliminate the source of conflict.
解析
解析:A 正确。Scrum Master 的职责是促进解决,而不是上报或强加决定。先一对一、再共同对话,能让双方都被听到,并由团队自己拥有解决方案,符合仆人式领导。上报产品负责人(C)绕过了团队自主权;移除成员(D)处理过重;简单投票(B)没有触及冲突根源,还可能埋下怨气。
Rationale:A is correct. The Scrum Master's role is to facilitate resolution, not escalate or impose decisions. A structured one-on-one followed by a joint conversation allows both parties to be heard and empowers the team to own the solution: consistent with servant leadership. Escalating to the PO (C) bypasses team autonomy. Removing a developer (D) is disproportionate. A simple vote (B) doesn't address the underlying conflict and may create resentment.
同考点练习题
-
PMP202611-012 · 答案 B
-
PMP202611-028 · 答案 B
-
PMP202611-036 · 答案 B
-
PMP202611-040 · 答案 B
-
PMP202611-097 · 答案 B
-
PMP202611-152 · 答案 B
-
PMP202611-166 · 答案 C
-
PMP202611-227 · 答案 B