定量风险分析:EMV与决策树 · PMP 练习题解析

风险管理 中等 Process 过程域 题号 PMP202611-242

题目

你需要在两个成本不同、收益不确定的解决方案之间做选择。哪种技术能在不确定条件下量化各方案的期望价值?
You need to decide between two solution options with different costs and uncertain payoffs. Which technique helps quantify the expected value of each option under uncertainty?

选项

  1. A.A simple list of pros and cons.
  2. B.A responsibility assignment matrix.
  3. C.A stakeholder engagement assessment matrix.
  4. D.Decision tree analysis using expected monetary value.
正确答案:D

解析

解析:结合预期货币价值的决策树分析,通过概率加权收益来量化不确定条件下的各方案。优缺点清单是定性方法;另两个矩阵分别用于职责与参与度,与财务价值无关。 Rationale:Decision tree analysis with expected monetary value quantifies options under uncertainty by weighting payoffs by probability. A pros-and-cons list is qualitative; the two matrices track responsibilities and engagement, not financial value.

同考点练习题