题目
你需要在两个成本不同、收益不确定的解决方案之间做选择。哪种技术能在不确定条件下量化各方案的期望价值?
You need to decide between two solution options with different costs and uncertain payoffs. Which technique helps quantify the expected value of each option under uncertainty?
选项
- A.A simple list of pros and cons.
- B.A responsibility assignment matrix.
- C.A stakeholder engagement assessment matrix.
- D.Decision tree analysis using expected monetary value.
解析
解析:结合预期货币价值的决策树分析,通过概率加权收益来量化不确定条件下的各方案。优缺点清单是定性方法;另两个矩阵分别用于职责与参与度,与财务价值无关。
Rationale:Decision tree analysis with expected monetary value quantifies options under uncertainty by weighting payoffs by probability. A pros-and-cons list is qualitative; the two matrices track responsibilities and engagement, not financial value.