质量保证与审计 · PMP 练习题解析

质量管理 中等 Process 过程域 题号 PMP202611-239

题目

质量审计发现团队确实按规定流程执行,但流程本身产出的结果很差。最合适的行动是什么?
A quality audit finds the team is following processes correctly but the processes themselves are producing poor outcomes. What is the most appropriate action?

选项

  1. A.Enforce the existing processes more strictly.
  2. B.Improve the processes themselves through process analysis.
  3. C.Add more audits of how people follow the processes.
  4. D.Accept the outcomes since the processes are being followed.
正确答案:B

解析

解析:当合规的流程产出糟糕结果时,需要改进流程本身,这就是持续过程改进。更严格执行有缺陷的流程只会产出更多坏结果;增加合规审计则误判了问题所在。 Rationale:When compliant processes yield poor results, the processes need improving — that is continuous process improvement. Enforcing flawed processes harder produces more bad outcomes; more compliance audits miss that compliance is not the problem.