题目
执行到中途你发现,项目风险登记册自规划阶段以来从未更新。最好的做法是什么?
Midway through execution you discover the project's risk register has not been updated since planning. What is the BEST action?
选项
- A.Use the original register since it was thorough at planning.
- B.Re-engage the team to identify new risks and reassess existing ones.
- C.Wait until the next phase gate to revisit risks.
- D.Delete outdated risks to keep the register short.
解析
解析:风险管理是迭代过程,应在执行过程中持续与团队重新识别和重估风险。依赖过时登记册会漏掉新出现的风险;等待则让项目处于裸奔状态。
Rationale:Risk management is iterative, so risks are re-identified and reassessed with the team throughout execution. Relying on a stale register ignores newly emerged risks; waiting leaves the project exposed.