风险管理计划与过程 · PMP 练习题解析

风险管理 困难 Process 过程域 题号 PMP202611-234

题目

执行到中途你发现,项目风险登记册自规划阶段以来从未更新。最好的做法是什么?
Midway through execution you discover the project's risk register has not been updated since planning. What is the BEST action?

选项

  1. A.Use the original register since it was thorough at planning.
  2. B.Re-engage the team to identify new risks and reassess existing ones.
  3. C.Wait until the next phase gate to revisit risks.
  4. D.Delete outdated risks to keep the register short.
正确答案:B

解析

解析:风险管理是迭代过程,应在执行过程中持续与团队重新识别和重估风险。依赖过时登记册会漏掉新出现的风险;等待则让项目处于裸奔状态。 Rationale:Risk management is iterative, so risks are re-identified and reassessed with the team throughout execution. Relying on a stale register ignores newly emerged risks; waiting leaves the project exposed.