题目

高层变更了组织战略,你的项目已不再符合新方向。最好的应对是什么?
Senior leadership changes the organisation's strategy, and your project no longer aligns with the new direction. What is the BEST response?

选项

  1. A.Continue unchanged because the project is already underway.
  2. B.Raise the misalignment with governance to decide whether to pivot, pause or stop the project.
  3. C.Pivot the project on your own to fit the new strategy.
  4. D.Hide the misalignment to protect the project's funding.
正确答案:B

解析

解析:把错位问题摆到台面上,才能由治理层依据新战略决定项目去留。继续推进可能交付无人需要的东西;自行转向或隐瞒则越权并损害组织。 Rationale:Surfacing the misalignment lets governance decide the project's fate against the new strategy. Continuing risks delivering something no longer wanted; pivoting or hiding exceeds your authority and harms the organisation.