题目
项目交付物已完成,但交付后组织并未跟踪预期效益是否实现。为什么这很重要?
Your project's deliverable is complete, but after delivery the organisation is not tracking whether the expected benefits are achieved. Why does this matter?
选项
- A.It does not matter once the deliverable is handed over.
- B.Because the project manager's bonus depends on it.
- C.Because benefits are guaranteed once the output is delivered.
- D.Because without measuring benefits, the organisation cannot confirm the project delivered value.
解析
解析:衡量效益是组织确认价值是否真正实现的方式,而这正是做项目的意义。仅仅交付并不能保证被采纳或产生成果。
Rationale:Measuring benefits is how the organisation confirms real value was delivered, which is the whole point of the project. Delivery alone does not guarantee adoption or outcomes.