题目
在供应商选择过程中,一家投标供应商给你送来贵重礼品。你应该怎么做?
During vendor selection, a bidding vendor sends you an expensive gift. What should you do?
选项
- A.Accept it quietly.
- B.Decline the gift, follow the organisation's policy and disclose it.
- C.Accept it and give the vendor a higher score.
- D.Share it with the team.
解析
解析:在供应商选择期间收礼会造成利益冲突。拒收并披露既维护公平,也保护个人诚信;具体处置以组织政策为准。
Rationale:Accepting gifts during selection creates a conflict of interest. Declining and disclosing protects fairness and your integrity; organisational policy governs the exact steps.