商业环境与战略 中等 Business Environment 商业环境域 题号 PMP202611-199

题目

PMO 要求每周提交 20 页状态报告,你的敏捷团队认为这很浪费时间。你应该怎么做?
The PMO requires a 20-page status report every week. Your agile team feels it wastes time. What should you do?

选项

  1. A.Stop sending the reports.
  2. B.Work with the PMO to tailor reporting so it meets the PMO's needs with lighter agile artifacts.
  3. C.Ask the team to work overtime on reports.
  4. D.Escalate a complaint about the PMO.
正确答案:B

解析

解析:治理有其目的,应与之协作而非绕开。裁剪既保留其意图(可见性与控制),又消除浪费;无视 PMO 会破坏信任。 Rationale:Governance serves a purpose, so work with it rather than around it. Tailoring keeps the intent (visibility and control) while removing waste; ignoring the PMO damages trust.