商业价值与价值交付 · PMP 练习题解析

商业环境与战略 中等 Business Environment 商业环境域 题号 PMP202611-196

题目

项目中期因并购导致原商业论证不再成立。你应该怎么做?
Mid-project, a merger means your project's business case is no longer valid. What should you do?

选项

  1. A.Finish the project as planned.
  2. B.Inform the sponsor and recommend reviewing whether to continue, change or close the project.
  3. C.Close the project yourself.
  4. D.Keep the news within the team.
正确答案:B

解析

解析:商业论证由发起人负责,项目是否继续也由其决策。你的职责是及时提出并给出清晰分析;自行关闭项目属于越权。 Rationale:The sponsor owns the business case and decides whether the project continues. Your role is to raise the issue promptly with clear analysis; closing it yourself exceeds your authority.