整合管理 中等 Process 过程域 题号 PMP202611-189

题目

开发与测试团队发现彼此一直在使用不同版本的需求文档。你应该怎么做?
The development and testing teams find they have been working from different versions of the requirements document. What should you do?

选项

  1. A.Ask the testers to use the developers' version.
  2. B.Set up version control so everyone works from one approved, current version.
  3. C.Let each team keep its own copy.
  4. D.Rewrite the requirements from scratch.
正确答案:B

解析

解析:配置与版本控制能建立单一事实来源,避免因文档不一致造成的返工与缺陷。 Rationale:Configuration and version control create a single source of truth, preventing rework and defects caused by mismatched documents.