定义活动与活动清单 · PMP 练习题解析

进度管理 中等 Process 过程域 题号 PMP202611-186

题目

WBS 中某个工作包过于笼统,团队无法估算。你应该怎么做?
The team cannot estimate a large work package in the WBS because it is too vague. What should you do?

选项

  1. A.Use a random estimate.
  2. B.Decompose the work package into smaller pieces, or plan it in more detail later using rolling wave planning.
  3. C.Remove it from scope.
  4. D.Ask the sponsor for the estimate.
正确答案:B

解析

解析:分解能让工作小到足以估算。若细节尚不清楚,滚动式规划先细化近期工作,远期工作保持较粗粒度。 Rationale:Decomposition makes work small enough to estimate. Where details are not yet known, rolling wave planning details near-term work and leaves later work at a higher level.