题目
WBS 中某个工作包过于笼统,团队无法估算。你应该怎么做?
The team cannot estimate a large work package in the WBS because it is too vague. What should you do?
选项
- A.Use a random estimate.
- B.Decompose the work package into smaller pieces, or plan it in more detail later using rolling wave planning.
- C.Remove it from scope.
- D.Ask the sponsor for the estimate.
解析
解析:分解能让工作小到足以估算。若细节尚不清楚,滚动式规划先细化近期工作,远期工作保持较粗粒度。
Rationale:Decomposition makes work small enough to estimate. Where details are not yet known, rolling wave planning details near-term work and leaves later work at a higher level.