成本管理 中等 Process 过程域 题号 PMP202611-183

题目

风险登记册中已识别的一项风险发生了,其既定应对措施需花费 300,000。应动用哪项储备金支付?
A risk listed in your risk register occurs, and its planned response costs 300,000. Which reserve should pay for it?

选项

  1. A.Management reserve.
  2. B.Contingency reserve.
  3. C.The team's training budget.
  4. D.The sponsor's personal budget.
正确答案:B

解析

解析:应急储备用于已识别的风险(已知的未知),属于成本基准的一部分。管理储备用于未识别风险,需管理层批准动用。 Rationale:Contingency reserve covers identified risks (known unknowns) and is part of the cost baseline. Management reserve covers unidentified risks and requires management approval.