沟通管理 中等 Process 过程域 题号 PMP202611-180

题目

相关方反馈项目邮件太多,反而漏掉了重要更新。你应该怎么做?
Stakeholders say they receive too many project emails and miss important updates. What should you do?

选项

  1. A.Send even more emails marked urgent.
  2. B.Review the communications plan with stakeholders and tailor the format and frequency, such as a weekly dashboard.
  3. C.Stop sending updates.
  4. D.Send updates only to the sponsor.
正确答案:B

解析

解析:沟通应匹配相关方的需要。调整形式与频率能让更新真正被看见;停止或缩小范围则会制造新的信息缺口。 Rationale:Communication should match stakeholders' needs. Tailoring format and frequency makes updates useful and visible; stopping or narrowing them creates new information gaps.