题目
某供应商的交付物屡次达不到合同约定的质量标准。你首先应该做什么?
A vendor's deliveries repeatedly fail the quality standard written in the contract. What should you do first?
选项
- A.Stop paying the vendor.
- B.Review the contract terms and formally raise the issue with the vendor as the contract requires.
- C.Find a new vendor immediately.
- D.Accept the deliveries to avoid delay.
解析
解析:合同是双方关系的法律基础。按合同条款处理既能保护项目,也给供应商纠正的机会。未经正当程序停付或换供应商会带来法律风险。
Rationale:The contract is the legal basis of the relationship. Following its terms protects the project and gives the vendor a chance to correct. Stopping payment or switching vendors without due process can create legal risk.
同考点练习题
-
PMP202611-065 · 答案 B