题目
产品负责人因缺少用户文档而拒收某个冲刺增量,而团队原以为不需要文档。最好的做法是什么?
The product owner rejects a sprint increment because user documentation is missing. The team thought documentation was not needed. What is the best action?
选项
- A.Ask the product owner to accept it anyway.
- B.Review and clarify the definition of done with the team and product owner.
- C.Write the documentation yourself.
- D.Remove documentation from all future work.
解析
解析:根本原因是“完成定义”不清晰。共同确认后即可避免后续冲刺再次被拒;绕过问题则根因仍在。
Rationale:The root cause is an unclear definition of done. Agreeing it together prevents the same rejection in future sprints; working around it leaves the cause in place.