题目
某关键路径任务已延误两周,发起人不会批准额外预算。最适合用来追回进度的技术是什么?
A critical path task is two weeks late. The sponsor will not approve extra budget. Which technique is most suitable to recover the schedule?
选项
- A.Crashing.
- B.Fast tracking.
- C.Cutting testing without approval.
- D.Reducing scope without telling the customer.
解析
解析:快速跟进通过并行开展活动来压缩工期,通常不增加直接成本,但会提高风险。赶工需要增加资源和成本,已被发起人排除;擅自削减测试或范围则违反质量与变更规则。
Rationale:Fast tracking overlaps activities and normally adds no direct cost, although it increases risk. Crashing adds resources and cost, which the sponsor has ruled out; cutting testing or scope without approval breaches quality and change rules.