进度压缩与赶工 · PMP 练习题解析

进度管理 中等 Process 过程域 题号 PMP202611-177

题目

某关键路径任务已延误两周,发起人不会批准额外预算。最适合用来追回进度的技术是什么?
A critical path task is two weeks late. The sponsor will not approve extra budget. Which technique is most suitable to recover the schedule?

选项

  1. A.Crashing.
  2. B.Fast tracking.
  3. C.Cutting testing without approval.
  4. D.Reducing scope without telling the customer.
正确答案:B

解析

解析:快速跟进通过并行开展活动来压缩工期,通常不增加直接成本,但会提高风险。赶工需要增加资源和成本,已被发起人排除;擅自削减测试或范围则违反质量与变更规则。 Rationale:Fast tracking overlaps activities and normally adds no direct cost, although it increases risk. Crashing adds resources and cost, which the sponsor has ruled out; cutting testing or scope without approval breaches quality and change rules.