每个用户验收测试轮次中,用户都会发现同一类型的缺陷。最好的做法是什么?
Users find the same type of defect in every user acceptance test cycle. What is the best action?
选项
- A.Add more testers at the end.
- B.Do a root cause analysis and improve the process so defects are prevented.
- C.Ask users to test less strictly.
- D.Accept the defects as normal.
解析
解析:质量管理强调预防优于检查。根本原因分析能消除重复缺陷的来源;在末端增加测试只会更晚、更贵地发现问题。
Rationale:Quality management prefers prevention over inspection. Root cause analysis removes the source of recurring defects; more end-stage testing only finds them later and more expensively.