风险管理计划与过程 · PMP 练习题解析

风险管理 困难 Process 过程域 题号 PMP202611-171

题目

某供应商的工人罢工,此事并未记录在你的风险登记册中,交付已经中断。你应该怎么做?
A supplier's workers go on strike. This was not in your risk register, and deliveries stop. What should you do?

选项

  1. A.Wait for the strike to end.
  2. B.Assess the impact, apply a workaround such as an alternate supplier, and update the issue log and risk register.
  3. C.Tell the sponsor the project will be late.
  4. D.Cancel the contract immediately.
正确答案:B

解析

解析:未识别的风险一旦发生即为问题,需要采取权变措施,随后记录归档以覆盖未来类似风险。未核查合同条款就取消合同可能带来法律风险。 Rationale:An unplanned risk that has occurred is an issue and needs a workaround, after which it is recorded so similar risks are covered later. Cancelling a contract without checking its terms may create legal exposure.