题目
在一个预测型项目中,客户要求增加一份不在已批准范围内的报告。你首先应该做什么?
In a predictive project, the client asks for a new report that is not in the approved scope. What should you do first?
选项
- A.Add the report because the client is important.
- B.Refuse the request.
- C.Analyse the impact on scope, schedule, cost and risk, then submit a change request.
- D.Ask the team to build it in their free time.
解析
解析:预测型项目采用整合变更控制:先评估影响,再由变更控制委员会或授权人决策。直接加活就是范围蔓延。
Rationale:Predictive projects use integrated change control: assess impact first, then the change control board or authorised person decides. Simply adding work is scope creep.
同考点练习题
-
PMP202611-047 · 答案 B
-
PMP202611-145 · 答案 C
-
PMP202611-174 · 答案 B
-
PMP202611-308 · 答案 C
-
PMP202611-360 · 答案 D
-
PMP202611-490 · 答案 C
-
PMP202611-541 · 答案 C