范围管理 困难 Process 过程域 题号 PMP202611-168

题目

在一个预测型项目中,客户要求增加一份不在已批准范围内的报告。你首先应该做什么?
In a predictive project, the client asks for a new report that is not in the approved scope. What should you do first?

选项

  1. A.Add the report because the client is important.
  2. B.Refuse the request.
  3. C.Analyse the impact on scope, schedule, cost and risk, then submit a change request.
  4. D.Ask the team to build it in their free time.
正确答案:C

解析

解析:预测型项目采用整合变更控制:先评估影响,再由变更控制委员会或授权人决策。直接加活就是范围蔓延。 Rationale:Predictive projects use integrated change control: assess impact first, then the change control board or authorised person decides. Simply adding work is scope creep.