题目
项目进行到一半,你才得知某监管事务团队必须在产品发布前完成审批,而他们此前不在你的相关方登记册中。你首先应该做什么?
Halfway through the project, you learn that a regulatory affairs team must approve the product before launch. They were not in your stakeholder register. What should you do first?
选项
- A.Wait until launch to involve them.
- B.Add them to the stakeholder register, analyse their interest and influence, and plan how to engage them.
- C.Ask the sponsor to get their approval.
- D.Change the launch date.
解析
解析:相关方识别贯穿项目全过程。发现新相关方后,应先分析并规划参与策略;在了解其需求之前就改发布日期为时过早。
Rationale:Stakeholder identification continues throughout the project. Once you find a new stakeholder, you analyse them and plan engagement; changing the date before you understand their needs is premature.