识别相关方与登记册 · PMP 练习题解析

相关方管理 中等 People 人域 题号 PMP202611-162

题目

项目进行到一半,你才得知某监管事务团队必须在产品发布前完成审批,而他们此前不在你的相关方登记册中。你首先应该做什么?
Halfway through the project, you learn that a regulatory affairs team must approve the product before launch. They were not in your stakeholder register. What should you do first?

选项

  1. A.Wait until launch to involve them.
  2. B.Add them to the stakeholder register, analyse their interest and influence, and plan how to engage them.
  3. C.Ask the sponsor to get their approval.
  4. D.Change the launch date.
正确答案:B

解析

解析:相关方识别贯穿项目全过程。发现新相关方后,应先分析并规划参与策略;在了解其需求之前就改发布日期为时过早。 Rationale:Stakeholder identification continues throughout the project. Once you find a new stakeholder, you analyse them and plan engagement; changing the date before you understand their needs is premature.

同考点练习题