题目
你新组建的敏捷团队不断请你去分派每日任务。你应该怎么做?
Your newly formed agile team keeps asking you to assign their daily tasks. What should you do?
选项
- A.Assign the tasks so work is not delayed.
- B.Coach the team to pull work from the sprint backlog and decide among themselves.
- C.Ask the product owner to assign the tasks.
- D.Ask the functional managers to assign the tasks.
解析
解析:在敏捷团队中,项目经理是服务型领导者,要培育团队自组织。辅导团队自行拉取工作能培养主人翁意识;由你分派任务只会让团队持续依赖你。
Rationale:In agile teams the project manager acts as a servant leader who builds self-organisation. Coaching the team to pull work develops ownership; assigning tasks yourself keeps the team dependent on you.