题目
某数字健康团队正在设计一款组织内的首创产品,在竞争市场中也不多见。规划与审计耗时较多。团队报告返工很少、客户投诉极少,但预算明显高于以往项目的常规基准。项目经理正在分析质量总成本,应该怎么做?
A digital health team is designing a new product that is a pioneering effort for the organization and one of few in a competitive market. Planning and auditing have been time-consuming. The team reports limited rework and minimal customer complaints, but the budget significantly exceeds typical baselines. The project manager is analyzing the total cost of quality. What should the project manager do?
选项
- A.Maintain the planned investment, appraisal, and prevention cost plan to reduce failure costs
- B.Increase prevention costs to maintain stability, reduce failure costs, and support the pace of change
- C.Reduce internal costs to increase time to deliver value on schedule and on budget and reduce failure costs
- D.Increase internal failure costs to detect defects early and minimize risks
解析
解析:项目呈现高一致性成本(规划、审计、预防与评估)和低非一致性成本(返工少、投诉少)。医疗领域的外部失败成本可能极为严重,因此明智做法是维持既定的预防与评估投入,而不是继续加码或削减。
Rationale:The project shows high cost of conformance (planning, auditing, prevention, appraisal) and low cost of nonconformance (little rework, few complaints). In healthcare, external failure costs can be catastrophic, so the effective strategy is to maintain the planned prevention and appraisal investment rather than increase or cut it.
同考点练习题
-
PMP202611-108 · 答案 D
-
PMP202611-487 · 答案 D