结束项目与阶段收尾 · PMP 练习题解析

整合管理 困难 Process 过程域 题号 PMP202611-140

题目

某项目团队一个月前把新 IT 系统的第一阶段移交给运维团队。项目团队现在正开展下一阶段工作,却不断被运维关键用户用新发现的问题打断。项目经理应如何避免将来再出现这种情况?
A project team released the first phase of a new IT system to the operations team a month ago. The project team is now working on the next phase but is continually contacted by operations key users with new findings. What should the project manager do to avoid this situation in the future?

选项

  1. A.Work with the product owner to review the operations handover process and checklist
  2. B.Have the project team prepare lessons learned starting from the first phase
  3. C.Request that all users contact technical support to submit change requests
  4. D.Stop operations users from coming back with new requirements since the first phase is over
正确答案:A

解析

解析:反复被打断的根因是移交过程不健全。阶段收尾需要正式移交,明确支持渠道与验收标准。审查并改进移交流程与检查清单,能从根本上解决未来阶段的验收与问题流转问题。 Rationale:The repeated interruptions stem from an ineffective transition process. Closing a phase requires a formal handover with defined support channels and acceptance criteria. Reviewing and fixing the handover process and checklist addresses the root cause so future phases are properly accepted and routed.

同考点练习题