财务指标与投资决策 · PMP 练习题解析

成本管理 困难 Process 过程域 题号 PMP202611-135

题目

一个为期两年的项目进行到一半时,由于全球供应链中断,某种关键原材料成本涨到三倍。更新后的成本估算已超出批准预算 35%,按修订后的成本预测,项目净现值(NPV)已转为负值。项目经理应建议什么?
Halfway through a two-year project, the cost of a critical raw material has tripled due to global supply chain disruptions. The updated cost estimate now exceeds the approved budget by 35%, and the project's net present value (NPV) has turned negative with the revised cost projections. What should the project manager recommend?

选项

  1. A.Request additional funding from the sponsor to complete the project as originally planned
  2. B.Present the updated financial analysis to the governance board with a recommendation to evaluate whether the project should continue, be restructured, or be terminated
  3. C.Reduce project scope significantly to fit within the original budget constraints
  4. D.Switch to lower-quality alternative materials to bring costs back within the approved budget
正确答案:B

解析

解析:当项目商业论证的基本面发生剧变(NPV 转负)时,项目经理应向治理机构提交更新后的财务分析,由其做继续/终止决策。继续推进已不再产生正业务价值的项目必须获得治理层明确批准;削减范围或降低质量并非项目经理可自行决定。 Rationale:When a project's business case fundamentals change dramatically (NPV turns negative), the PM presents the updated financial analysis to the governance body for a go/no-go decision. Continuing a project that no longer delivers positive business value requires explicit governance approval; scope cuts or quality compromises are not the PM's call.

同考点练习题