题目
一个为期两年的项目进行到一半时,由于全球供应链中断,某种关键原材料成本涨到三倍。更新后的成本估算已超出批准预算 35%,按修订后的成本预测,项目净现值(NPV)已转为负值。项目经理应建议什么?
Halfway through a two-year project, the cost of a critical raw material has tripled due to global supply chain disruptions. The updated cost estimate now exceeds the approved budget by 35%, and the project's net present value (NPV) has turned negative with the revised cost projections. What should the project manager recommend?
选项
- A.Request additional funding from the sponsor to complete the project as originally planned
- B.Present the updated financial analysis to the governance board with a recommendation to evaluate whether the project should continue, be restructured, or be terminated
- C.Reduce project scope significantly to fit within the original budget constraints
- D.Switch to lower-quality alternative materials to bring costs back within the approved budget
解析
解析:当项目商业论证的基本面发生剧变(NPV 转负)时,项目经理应向治理机构提交更新后的财务分析,由其做继续/终止决策。继续推进已不再产生正业务价值的项目必须获得治理层明确批准;削减范围或降低质量并非项目经理可自行决定。
Rationale:When a project's business case fundamentals change dramatically (NPV turns negative), the PM presents the updated financial analysis to the governance body for a go/no-go decision. Continuing a project that no longer delivers positive business value requires explicit governance approval; scope cuts or quality compromises are not the PM's call.