职业道德与合规 困难 Business Environment 商业环境域 题号 PMP202611-133

题目

项目经理发现某供应商在工料合同发票中持续虚增工时。该供应商是项目发起人的长期业务伙伴。项目经理应该怎么做?
A project manager discovers that a vendor has been consistently inflating hours on time-and-materials invoices. The vendor is a long-standing business partner of the project sponsor. What should the project manager do?

选项

  1. A.Discuss the issue privately with the vendor and ask them to correct future invoices
  2. B.Document the findings with evidence and report them through the organization's established ethics and governance channels
  3. C.Absorb the cost overrun since the discrepancy is within the project's contingency budget
  4. D.Discuss the matter with the sponsor first since the sponsor manages the vendor relationship
正确答案:B

解析

解析:道德违规与采购异常必须通过既定治理渠道上报,不受私人关系或组织政治影响。项目经理负有诚信行事的职业义务;与供应商或存在利益冲突的发起人私下处理可能影响调查。 Rationale:Ethical violations and procurement irregularities must be reported through established governance channels regardless of personal relationships or organizational politics. The PM has a professional obligation to act with integrity; discussing with the vendor or the sponsor (who has a conflict of interest) could compromise the investigation.