题目
某建筑项目团队需在两家建材供应商之间选择。供应商 A 价格低 12%,但环保合规记录较差;供应商 B 使用可持续采购材料与碳中和生产,但价格更高。项目商业论证明确包含可持续性目标。项目经理应建议选择哪家?
A construction project team must choose between two building material suppliers. Supplier A offers materials at 12% lower cost but has a poor environmental compliance record. Supplier B uses sustainably sourced materials and carbon-neutral manufacturing, but costs more. The project business case explicitly includes sustainability objectives. What should the project manager recommend?
选项
- A.Select Supplier A to minimize project costs and maximize return on investment
- B.Select Supplier B because sustainability requirements defined in the business case are project constraints that must be met
- C.Select Supplier A and offset the environmental impact by purchasing carbon credits separately
- D.Escalate the decision to the sponsor since it involves a cost versus sustainability tradeoff
解析
解析:当商业论证明确列出可持续性目标时,它们与成本、进度、范围一样构成项目约束。应建议满足全部约束(含可持续性要求)的方案;以违背既定约束为代价优化成本并不可取。
Rationale:When sustainability objectives are explicitly defined in the business case, they become project constraints alongside cost, schedule, and scope. Recommending the option that meets all constraints—including sustainability—is correct; cost optimization that violates stated constraints is not appropriate.