AI 与技术治理 困难 Business Environment 商业环境域 题号 PMP202611-128

题目

一名项目经理负责大型基础设施项目,可以使用 AI 驱动的预测分析工具。该工具依据历史项目数据与当前绩效趋势,预测测试阶段有 78% 的概率延误两周。项目经理应该怎么做?
A project manager leading a large infrastructure project has access to an AI-powered predictive analytics tool. The tool forecasts a 78% probability of a two-week delay in the testing phase based on historical project data and current performance trends. What should the project manager do?

选项

  1. A.Immediately add two weeks of buffer to the project schedule based on the AI prediction
  2. B.Use the AI prediction as one input alongside team judgment and risk analysis to develop a proactive mitigation plan
  3. C.Disregard the prediction since AI tools are not yet reliable enough for project management decisions
  4. D.Report the predicted delay to the sponsor and request a schedule extension before investigating further
正确答案:B

解析

解析:AI 工具提供数据驱动的洞察,但应与人的判断、团队经验与风险分析共同作为输入。项目经理应借助预测主动制定减轻策略,而不是盲从或全盘否定;AI 辅助决策但不能替代专业判断。 Rationale:AI tools provide data-driven insight but should be one input alongside human judgment, team expertise, and risk analysis. The PM uses the prediction to proactively build mitigation strategies rather than blindly accepting or rejecting it; AI supports but does not replace professional judgment.