题目
项目经理发现,一项已由变更控制委员会(CCB)批准的关键可交付成果,现在与组织在该变更获批后更新的战略规划相冲突。项目经理应该怎么做?
A project manager discovers that a key deliverable approved by the change control board (CCB) now conflicts with the organization's strategic plan, which was updated after the change was approved. What should the project manager do?
选项
- A.Continue executing the approved change since it went through proper governance
- B.Raise the conflict with the project steering committee for guidance on how to proceed
- C.Reverse the approved change independently to align with the new strategy
- D.Document the conflict as a risk and continue execution
解析
解析:当已批准的决定与更新的组织战略冲突时,应上报治理机构(指导委员会)寻求指示。自行撤销已批准变更会绕过治理;仅把冲突记为风险则忽视了可能损害项目价值的战略错位。
Rationale:When approved decisions conflict with updated organizational strategy, escalate to the governance body (steering committee) for direction. Unilaterally reversing an approved change bypasses governance, and merely logging the conflict ignores the strategic misalignment that can undermine project value.
同考点练习题
-
PMP202611-092 · 答案 A
-
PMP202611-213 · 答案 B
-
PMP202611-220 · 答案 B
-
PMP202611-266 · 答案 A
-
PMP202611-418 · 答案 B
-
PMP202611-440 · 答案 A
-
PMP202611-519 · 答案 C