题目
某项目按时按预算完成,但上线三个月后,业务发起人反馈预期的客户留存率提升 15% 并未实现。项目经理应建议什么?
A project was completed on time and within budget, but three months after launch the business sponsor reports that the expected 15% increase in customer retention has not materialized. What should the project manager recommend?
选项
- A.Close the project formally since all deliverables were accepted during project closure
- B.Conduct a benefits review to identify gaps between delivered outputs and expected business outcomes
- C.Reopen the project and add new deliverables to achieve the retention target
- D.Escalate to the PMO for a full project audit
解析
解析:效益实现管理确保产出转化为业务成果。效益审查可解释为何可交付成果已完成但预期效益未实现的原因;直接关闭忽视业务目的,而在弄清差距前重启项目为时过早。
Rationale:Benefits realization management ensures outputs translate into business outcomes. A benefits review explains why expected benefits are not materializing even though deliverables were completed; closing the project ignores the business purpose, and reopening is premature before the gap is understood.
同考点练习题
-
PMP202611-068 · 答案 B
-
PMP202611-072 · 答案 B
-
PMP202611-193 · 答案 B
-
PMP202611-205 · 答案 C
-
PMP202611-210 · 答案 C
-
PMP202611-215 · 答案 D
-
PMP202611-316 · 答案 B
-
PMP202611-369 · 答案 A