效益实现与价值管理 · PMP 练习题解析

成本管理 困难 Process 过程域 题号 PMP202611-123

题目

某项目按时按预算完成,但上线三个月后,业务发起人反馈预期的客户留存率提升 15% 并未实现。项目经理应建议什么?
A project was completed on time and within budget, but three months after launch the business sponsor reports that the expected 15% increase in customer retention has not materialized. What should the project manager recommend?

选项

  1. A.Close the project formally since all deliverables were accepted during project closure
  2. B.Conduct a benefits review to identify gaps between delivered outputs and expected business outcomes
  3. C.Reopen the project and add new deliverables to achieve the retention target
  4. D.Escalate to the PMO for a full project audit
正确答案:B

解析

解析:效益实现管理确保产出转化为业务成果。效益审查可解释为何可交付成果已完成但预期效益未实现的原因;直接关闭忽视业务目的,而在弄清差距前重启项目为时过早。 Rationale:Benefits realization management ensures outputs translate into business outcomes. A benefits review explains why expected benefits are not materializing even though deliverables were completed; closing the project ignores the business purpose, and reopening is premature before the gap is understood.