满足质量要求的主要收益包括以下各项,除了:
All of the following are primary benefits of meeting quality requirements EXCEPT:
选项
- A.Less rework
- B.Increased productivity
- C.Lower costs
- D.Fewer change orders
解析
解析:满足质量要求可减少返工、提高生产率、降低成本,并提升相关方满意度与盈利能力。变更单减少并不属于这些主要收益。
Rationale:Meeting quality requirements reduces rework, raises productivity, lowers costs, and increases stakeholder satisfaction and profitability. Fewer change orders are not among the listed primary benefits.