题目
执行整合是所有项目经理的基础能力。以下描述了执行整合的三个层面,除了:
Performing integration is a foundational skill for all project managers. The following describe the three levels of performing integration EXCEPT:
选项
- A.Cognitive level
- B.Process level
- C.Complexity level
- D.Context level
解析
解析:整合发生在过程、认知与情境三个层面。复杂性是项目属性,而不是整合的层面。
Rationale:Integration takes place at the process, cognitive, and context levels. Complexity is a project attribute, not an integration level.