收集需求与需求管理 · PMP 练习题解析

范围管理 中等 Process 过程域 题号 PMP202611-106

题目

哪份文件把产品需求从其来源链接到可交付成果,确保每项需求都能带来业务价值,并为管理产品范围变更提供结构?
Which document links product requirements from their source to the deliverables, ensuring each requirement adds business value and providing a structure for managing changes to product scope?

选项

  1. A.Configuration management system
  2. B.Business case
  3. C.New product development matrix
  4. D.Requirements traceability matrix
正确答案:D

解析

解析:需求追溯矩阵把产品需求从其来源链接到满足它的可交付成果,确认需求与业务价值的关联,并在全生命周期跟踪需求,为范围变更控制提供支撑。 Rationale:The requirements traceability matrix is a grid linking product requirements from origin to the deliverables that satisfy them. It confirms business value linkage and tracks requirements through the life cycle, supporting scope change control.