质量管理计划与目的 · PMP 练习题解析

质量管理 中等 Process 过程域 题号 PMP202611-102

题目

项目质量管理包含将组织质量方针落实到项目与产品质量标准的方法,其目的是:
Project Quality Management encompasses the methods for implementing the organization's quality policy into project and product quality criteria in order to:

选项

  1. A.Meet the goals of stakeholders
  2. B.Enhance process capabilities
  3. C.Maintain control over products, services, and outcomes
  4. D.Meet the project team's performance standards
正确答案:A

解析

解析:质量管理把组织质量方针融入项目与产品质量要求的规划、管理与控制,最终目的是满足相关方目标。提升过程能力是手段而非目的。 Rationale:Quality management incorporates the organization's quality policy into planning, managing, and controlling project and product quality requirements in order to meet stakeholders' objectives. Enhanced process capability is a means, not the end.