题目
一名项目经理领导混合型项目(敏捷开发+预测型基础设施),发现开发团队的速率连续三个冲刺下降,成员在每日站会上显得压力大且投入度低。项目经理应如何应对?
A project manager leading a hybrid project (agile development with predictive infrastructure) notices that the development team's velocity has dropped for three consecutive sprints. Team members appear stressed and disengaged during daily standups. How should the project manager respond?
选项
- A.Set performance targets and warn the team about the consequences of continued low velocity
- B.Meet individually with team members to understand obstacles, remove impediments, and support their well-being
- C.Report the velocity drop to the sponsor and request additional resources
- D.Add more detailed reporting requirements so the team's work is more visible
解析
解析:仆人式领导把团队需求放在首位,重在排除障碍而非下达绩效命令。一对一沟通能识别原因究竟是技术、工作量还是个人问题,而设定目标或增加汇报都无法做到。
Rationale:Servant leadership puts the team's needs first and focuses on removing impediments rather than commanding performance. Individual conversations surface whether the causes are technical, workload-related, or personal, which targets like warnings or extra reporting cannot do.