整合管理 简单 Process 过程域 题号 PMP202611-095

题目

关键相关方与项目经理必须回答若干问题,以确定项目成功的衡量标准。以下都属于这类问题,除了:
Key stakeholders and project managers must answer several questions to develop measures of project success. All of the following are such questions EXCEPT:

选项

  1. A.What does success look like for the project?
  2. B.How will success be measured?
  3. C.What are the communication requirements?
  4. D.What factors may impact success?
正确答案:C

解析

解析:定义成功围绕三点:成功的样子、如何衡量、哪些因素会影响。沟通需求属于具体的沟通规划内容,不属于成功定义的范畴。 Rationale:Defining success centers on what success looks like, how it will be measured, and what factors may affect it. Communication requirements belong to detailed communications planning rather than to the definition of success.