整体变更控制 · PMP 练习题解析

整合管理 简单 Process 过程域 题号 PMP202611-093

题目

关于实施整体变更控制的工具与技术,以下哪项说法不正确?
Which statement is NOT true about the tools and techniques of Perform Integrated Change Control?

选项

  1. A.They include expert judgment
  2. B.They include change control meetings
  3. C.A change control board (CCB) meets to review change requests and approve, reject, or otherwise dispose of them
  4. D.They include project plan updates
正确答案:D

解析

解析:专家判断与变更控制会议(含 CCB)属于工具与技术。项目计划更新是该过程的输出,而不是工具与技术。 Rationale:Expert judgment and change control meetings (with the CCB) are tools and techniques. Project plan updates are an output of the process, not a tool or technique.

同考点练习题