题目
关于实施整体变更控制的工具与技术,以下哪项说法不正确?
Which statement is NOT true about the tools and techniques of Perform Integrated Change Control?
选项
- A.They include expert judgment
- B.They include change control meetings
- C.A change control board (CCB) meets to review change requests and approve, reject, or otherwise dispose of them
- D.They include project plan updates
解析
解析:专家判断与变更控制会议(含 CCB)属于工具与技术。项目计划更新是该过程的输出,而不是工具与技术。
Rationale:Expert judgment and change control meetings (with the CCB) are tools and techniques. Project plan updates are an output of the process, not a tool or technique.