管理团队:绩效与冲突 · PMP 练习题解析

资源管理 中等 People 人域 题号 PMP202611-088

题目

某项目出现进度绩效问题。经过评估,项目经理发现项目资源的知识水平偏低:少数资深资源在做无关工作,一些技能不足的资源完成任务耗时过长。项目经理应如何提升团队绩效?
A project is experiencing schedule performance issues. After assessing the issues, the project manager finds that project resources have low levels of knowledge. A few senior-level resources perform irrelevant work, and some unskilled resources take much too long to accomplish tasks. What should the project manager do to improve the team's performance?

选项

  1. A.Implement training where necessary and make work requirements more visible for all team members
  2. B.Reassign the senior-level resources as coaches and mentors to the inexperienced ones
  3. C.Give the junior team members incentives to work faster and send an email to the senior-level resources
  4. D.Remind the entire team of project goals, schedules, roles, and timelines during the next team meeting
正确答案:A

解析

解析:项目经理既要确保初级成员得到充分培训,也要确保每个人都在做分内之事。把培训与可视化的任务要求结合起来,才能同时解决两个根因;激励、发邮件或口头提醒都无法纠正技能与工作分配问题。 Rationale:The project manager must ensure junior members are adequately trained and that everyone is doing assigned work. Combining training with visible work requirements addresses both root causes; incentives, emails, or verbal reminders do not fix skill and workload misallocation.