沟通技巧:倾听反馈与情商 · PMP 练习题解析

沟通管理 困难 Process 过程域 题号 PMP202611-083

题目

一名项目经理负责一个规模不大但对大型项目群里程碑至关重要的项目。为替代一位不得不离开的关键资源,已分配了一名新资源。一位外部相关方声称,分配新资源的人把团队里最差的成员派了过来。项目经理应如何对待这个传言?
A project manager is working on a minor project that is fundamental to the success of a larger program milestone. To replace a critical resource who had to leave the project, a new resource has been assigned. An outside stakeholder claims that the person who assigned the new resource sent their worst team member. How should the project manager approach this rumor?

选项

  1. A.Assess the new resource's ability to perform the necessary work by testing their communication skills with the current project team
  2. B.Evaluate the skills of the new resource to see how the resource can provide value to the project
  3. C.File a request with the project management office (PMO) manager in order to obtain a better resource
  4. D.Address the rumor with the new resource's functional manager to mitigate any conflict within the project team
正确答案:B

解析

解析:在没有直接观察其绩效之前,传言未必属实。传闻属于关系风险,项目经理应先通过评估新资源的真实技能来弄清事实,再决定如何行动。 Rationale:The rumor may be false without first-hand observation of performance. Third-party information such as hearsay is a relationship risk, so the project manager should investigate the facts by evaluating the new resource's actual skills before acting on the claim.