项目经理的大部分时间都用于与团队成员和其他相关方沟通。为了有效沟通,项目经理必须完成以下所有事项,除了:
Project managers spend most of their time communicating with team members and other stakeholders. To communicate effectively, the project manager must perform all of the following EXCEPT:
选项
- A.Calculating the potential number of communication channels accurately
- B.Developing finely tuned skills using multiple methods of communication
- C.Incorporating feedback channels
- D.Seeking to understand project stakeholders' communication needs
解析
解析:有效沟通依赖多种沟通方式、反馈闭环以及对相关方需求的把握。计算理论沟通渠道数(n(n-1)/2)只是规划辅助手段,并非有效沟通的必要动作。
Rationale:Effective communication requires multiple methods, feedback loops, and understanding stakeholders' needs. Computing the theoretical number of channels (n(n-1)/2) is a planning aid, not a requirement for communicating effectively.